Construction of Groeipunt transmission substation in South Africa now 80% complete
Construction of the Kangas Wind Farm’s, Groeipunt transmission substation in the North West region of South Africa, is now 80% complete ahead of its handing over to the State-owned power utility, Eskom, in March next year. The construction works of the substation begun in June this year and marked the first time that an independent […]